Tuesday, July 18
|
|
| 8:00 |
Arrival at NIST and Check-in at Gate, Agenda |
|
|
| 8:30 |
Welcome
and Meeting Objectives |
Curt Davis,
Carol Johnson |
|
| 8:45 |
NOAA Prospective and Goals for
Meeting |
Stan Wilson
Kent Hughes |
|
| 9:00 |
MOBY
Background and Need for Replacement |
Dennis Clark |
|
| 9:30 |
RNO Concept: Design and Implementation |
Dennis Clark |
|
| 10:00 |
Coffee Break |
|
| 10:30 |
Description of AHAB Design
|
Mark Yarbrough
Steve Brown |
| 11:30 |
Plan to Complete and Test Re-engineered System |
Steve Brown |
| 12:00 |
Lunch |
|
| 1:00 |
Plan for Calibration and
Maintenance of AHAB
|
Carol Johnson
Ken Voss |
|
| 2:00 |
AHAB
Deployment Plan (Timeline) |
Dennis Clark |
| 2:30 |
Summary |
Carol Johnson |
|
| 3:00 |
Afternoon Break |
|
|
| 3:30 |
Group Discussion of Goals and Presentation, Development,
and Initial Outline of Report |
Curt Davis
Kent Hughes |
|
| 4:00 |
Review Team and NOAA Representatives Meet in a Closed Session |
|
|
| 4:45 |
Depart for Hotel |
|
|
Wednesday, July 19
|
|
| 8:00 |
Arrival at NIST and Check-in at Gate |
|
|
| 8:30 |
Review Team Reports their Initial Findings and Draft
Outline of the Report |
Curt Davis |
|
| 9:00 |
Discussions with the MOBY Team |
Curt Davis
Dennis Clark |
|
| 10:00 |
Coffee Break |
|
|
| 10:30 |
Review Team and NOAA Meeting in Closed Session to
Update Report Outline |
Curt Davis |
|
| 11:30 |
Reconvene for Discussion with the MOBY Team and
Develop Schedule for Completion of the Report |
Curt Davis
Dennis Clark |
|
| 12:00 |
Lunch |
|
|
| 1:00 |
Review Team Works on First Draft of the Report |
Curt Davis |
|
| 3:00 |
Coffee Break |
|
|
| 4:00 |
Adjourn |
|
|